No bridge in '07


Published/Last Modified on Monday, December 24, 2007 9:03 AM CST

JEFF MOORE, THE DAILY IBERIAN

New Iberia will not be getting a new bridge for Christmas, or New Year’s Day, for that matter, state Department of Transportation and Development officials said Friday.

The long-awaited Lewis Street bridge likely won’t be open for traffic before mid-January, said DOTD district engineer Bill Fontenot.

Traffic goes over the old Lewis Street Bridge while the new Lewis Street Bridge waits to be opened LEE BALL/THE DAILY IBERIAN

Advertisement
And the opening could stretch into February if testing of the bridge takes longer than expected.

“We wish it were better news, but that’s where we stand right now,” said DOTD spokesman Mark Lambert. “Obviously, we’d rather get this thing open sooner, but we’re not going to open it until it’s safe.”

Fontenot said contractors have run into problems with an electrical motor used in the raising and lowering of the vertical lift-span bridge.

Fontenot said the previous motor did not meet the standards required for the project, so contractors had to order a new one.

Fontenot said the new motor must be custom-made, a process that will take about a month.

He said the new motor should arrive by the second week of January.

In the meantime, Fontenot said, contractors have ordered a second, temporary motor, which should arrive on Wednesday.

That motor could allow workers to resume testing while they are waiting for the permanent replacement, which could save some time in the process.

“If everything would go perfect, and we reach a comfort level with those temporary motors, it would be a matter of just switching out the motors when the permanent ones come in,” Fontenot said.

The motor problems are just the latest setback in the construction of the bridge, which began in March 2004.

The $13.8 million bridge was originally expected to be open by September 2006, but the project was put on hold when workers were sent to New Orleans in the aftermath of Hurricane Katrina.

The DOTD recently set an expected date of completion of Dec. 7, but that date came and went after workers encountered problems with an electrical cable that supplies power to the bridge.

Then, during the testing of the cable, workers discovered problems with the motor, Fontenot said.

“It’s just been one thing after another,” Lambert said. “It seems like if something could go wrong, it did go wrong on this project.”

Lambert said many of the problems were beyond the control of the DOTD or the New Orleans-based contractor for the project, Boh Brothers Construction. He declined to say whether the company would face any penalties for the delays.

“Our focus right now isn’t trying to penalize anybody,” he said. “Our focus is trying to get that thing open as soon as possible.”

Comments

    Gayle Charpentier wrote on Dec 26, 2007 12:18 PM:

    " How can a contractor in mississippi build a new highway a mile or so long and high rise bridge 4 lane at that and completed in the same time this contractor has been working on the Lewis street bridge.Someone used poor jugdement on this contract.they coudent build a dog house for me . PS: THEY WOULD FORGET GET THE NAILS "

    Marcus wrote on Dec 25, 2007 11:04 AM:

    " It sounds like BOH Brothers has been taking lessons from Brown and Root on their projects. Can we expect to see any politicians from New Iberia in Washington when this bridge is complete? "

    John wrote on Dec 24, 2007 11:20 AM:

    " I'm just amazed at the amount of lies that Boh Brothers and LADOT can state about the Lewis Street Bridge. How can a custom manufactured motor, that should have been fully tested by the manufacturer, fail? How can you come up with a temporary motor that will work when you need a custom built motor? Why doesn't Boh use the temporary motor to open the bridge until the custom built motor is replaced? Just how long will we put up with these lies? Until we stand up to LADOT and politicians, nothing will change. Call or email them today. "

    danny wrote on Dec 24, 2007 9:54 AM:

    " come on if not one reason its another .these contractors mite have beenthe lowest bid but not the best for the job.i think moses built the ark faster then the contractors are builting this bridge. "

WRITE A COMMENT

Use the form below to post a brief comment related to this story. Use the word count tool to assist you in keeping your remarks to 100 words or fewer.

•Comments must be approved by an editor or the publisher before appearing on the Web site but are not verified for accuracy nor have we verified the identity of any person supposedly posting an comment. Please consider this as you consider any statement made. A thoughtful contribution to the online discussion is appreciated.

• Please note your comments must attempt to follow basic rules of grammar and punctuation or they will not be posted. Do not use unfamiliar abbreviations or text-like short cuts, like ur for your. Please keep your tone civil. You can say someone's idea is stupid but you cannot say someone is stupid.

• Comments should deal with matters of public concern. Problems with private individuals or private companies are not likely to get posted.

• Questions or comments about items posted should be e-mailed to dailyiberian@bellsouth.net.

(optional)
Current Word Count:
   

Classifieds


Contact Us

Subscribe
Vacation Hold
General Email

Mailing Address:
The Daily Iberian
P.O. Box 9290
New Iberia, LA
70562-9290

Street Address:
926 East Main St.
New Iberia, LA 70560

Phone:
(337) 365-6773

Fax:
(337)-367-9640

Inside Louisiana:
800-365-6773

Local Weather